How Long Does It Take to Tile a Bathroom?

What happens on each day of a bathroom tiling job, the stages you cannot rush, and the things that make a job take longer than expected.

Most bathrooms take a few days to tile, but the honest answer is that it depends on the size of the room, the tile you have chosen and, most of all, what state the walls and floor are in once the old tiles come off.

Rather than give a number that will be wrong for half the bathrooms out there, here is what happens at each stage, which parts cannot be rushed, and what tends to add time.

Stage 1: strip-out and inspection

If the room is being refitted, the old tiles come off first, along with old adhesive and anything loose behind them. This is where surprises turn up. Blown plaster, damp from a leaking shower, rotten boards under the bath and walls that are far from flat are all common, particularly in older houses.

This stage is often quicker than people expect, but what it reveals decides how long the rest of the job takes.

Stage 2: boarding, levelling and priming

Walls are made flat and sound, usually with tile backer board in the shower area and wherever the plaster is poor. Timber floors are overboarded so they do not flex. Uneven floors are levelled with a compound, which needs time to dry before tiling.

Surfaces are then primed so the adhesive bonds properly. You can read more about this stage on my preparation and waterproofing page.

Stage 3: tanking the wet areas

Around the shower and bath, the walls and floor are tanked with a waterproofing system before any tile goes on. Liquid membranes go on in coats, and each coat needs to dry as the manufacturer specifies. A wet room needs the whole floor tanked and laid to a fall, which takes longer again. What is a wet room explains that build in more detail.

This is one of the stages that cannot be squeezed. Tiling over waterproofing that has not cured is how leaks start.

Stage 4: setting out and tiling

Before the first tile is fixed, the layout is worked out so the cuts fall in sensible places and the full tiles sit where you look. On a simple room this is quick. With a feature wall, a niche, a herringbone floor or large format tiles, it takes longer, and it is time well spent.

Then the walls and floor are tiled. How fast this goes depends on:

  • Tile size. Very small tiles and mosaics take longer per square metre. Very large tiles are quicker to cover an area but slower to handle, level and cut.
  • Tile type. Porcelain is harder to cut and drill than ceramic. Natural stone needs sorting, sealing and careful handling.
  • The number of cuts. Pipes, windows, boxed-in soil stacks and niches all add cuts.
  • Pattern. Herringbone and diagonal layouts take noticeably longer than a straight lay.

Stage 5: grouting and sealing

Adhesive needs to set before grouting, so grout usually goes in on a later visit. After grouting, silicone goes around the bath, tray and corners. Natural stone is sealed again at the end.

The room should then be left for the grout and silicone to cure before the shower is used. The product instructions will say how long.

What usually adds time

  • Walls or floors that need more work than expected once the old tiles are off.
  • Tiles arriving late, damaged or from different batches, which do not match.
  • Waiting on other trades, such as the plumber fitting a shower valve or the electrician moving a fan.
  • Changes of plan mid-job, such as adding a niche or extending the tiling to full height.
  • Drying times for levelling compound, tanking and grout, which cannot be skipped.

How to keep it on track

Have the tiles delivered, checked and counted before the start date, with around 10% extra for cuts. Agree the layout and grout colour in advance. Make sure the plumber knows when first fix needs to be done. And expect the bathroom to be out of use for the duration, so plan around a second toilet or shower if you have one.

When I quote, I'll give you a realistic timescale based on what I see, rather than an optimistic one.

I tile bathrooms and en-suites across Chelmsford, Great Baddow and South Woodham Ferrers. See bathroom and wet room tiling, wall tiling and floor tiling, then send me your measurements or call 07792 959839 for a free quote.

Quick answers

How long does it take to tile a small bathroom?

A small, straightforward bathroom is usually a few days, including preparation, tiling and grouting on separate visits. More preparation or a complex layout adds time.

Can I use the shower straight after tiling?

No. The grout and silicone need to cure first. Follow the product instructions, and ask your tiler when it is safe to use.

Why does the tiler come back on different days?

Levelling compound, tanking and adhesive all need drying or setting time before the next stage. Rushing those stages is the most common cause of failed tiling.